Scheduling Asset Physical Verification
- Chilukuri Srinivasa Reddy (Unlicensed)
- Shilpa K (Deactivated)
- Mayuresh Balaji Kamble (Unlicensed)
Variance
Import
Importing and Allocating Assets in Bulk
Activating or Deactivating and Moving Assets in Bulk
Approvals
Verifying Asset Reconciliation
Approving Physically Verified Assets
Approving Store Wise Reconciled Assets
Approving Asset Using Maker-checker
Contract Management
Adding Contract or Agreement Details
Software Delivery
Configuring Software Delivery Schedule
Viewing Software Delivery Status
Viewing Software Uninstallation Report
Configuring Asset Management Module
Configuring Asset Category Using Form Builder
Configuring My Asset List Page
Asset Masters
Configuring Location And Store
Configuring Notifications and Templates
Configuring Allocation Form Template
Configuring Field Display Order on Fixed Asset List Page
Software
Configuring Software Baseline Profiles
Software Baseline Profile Mapping
Depreciation
Configuring Depreciation Formula
Configuring Depreciation Field Mapping
Configuring Custom Depreciation Formula
Mapping
Configuring Custom Hardware Variance
Configuring Application Control Messages
Configure Software and Executable Execution Type
Endpoint Automation Profile Mapping
Others
Configuring Asset Application Settings
Configuring Asset Scan Domain List
Configuring Local Password Management
Configuring E-mail Notifications
Configuring Asset Integration Details
Configuring Additional Discovery
Scheduling Asset Physical Verification
Adding Software Deployment Profile
Approval Matrix
Deactivation Approval Matrix
Configuring Deactivation Approval Matrix
You can request for Physical Verification of the Assets by scheduling the frequencies so that the Verification process of the Assets is started at the set date and time.
To schedule Asset Physical Verification:
- Select Asset > Configuration > Others > Asset Physical Verification.
- On the ACTIONS panel of the ASSET PHYSICAL VERIFICATION page, click ADD NEW. The ASSET PHYSICAL VERIFICATION configuration page is displayed. Fill in the required details and click SUBMIT. For more information about the fields on the ASSET PHYSICAL VERIFICATION page, see Field Description.
Figure: ASSET PHYSICAL VERIFICATION page
Field Description
The following table describes the fields on the ASSET PHYSICAL VERIFICATION page:
Field | Description |
---|---|
Category | Select the Asset Category from the drop-down list. |
Request Type | Select the Physical Verification Request Type from the drop-down list. |
Stores | The field is displayed if you select Store in the Request Type drop-down list. Select the Stores from the drop-down list for which you want to schedule a Physical Verification process. |
Floors | The field is displayed if you select Floor in the Request Type drop-down list. Select the Floors from the drop-down list for which you want to schedule a Physical Verification process. |
Customers | The field is displayed if you select Customer in the Request Type drop-down list. Select the Customers from the drop-down list for whom you want to schedule a Physical Verification process. |
Notify To | Specify the E-mail Ids of the users to whom you want to notify during the Physical Verification process. |
Active | If selected, the Physical Verification configuration becomes active. |
Enable Exclude Options | If selected, the EXCLUDE SECTION is displayed where you can specify certain criteria for the Assets to exclude these Assets from the Physical Verification process. |
EXCLUDE SECTION | |
Assets Allocated Within | Specify the number of days in the Assets Allocated Within field. The Assets that are allocated within the specified days, are excluded from the Physical Verification process. |
Physical Verification done for Assets Within | Specify the number of days in the Physical Verification done for Assets Within field. The Assets that are already verified within the specified days, are excluded from the Physical Verification process. |
Asset Reconciliation done Within | Specify the number of days in the Asset Reconciliation done Within field. The Assets that are reconciled within the specified days, are excluded from the Physical Verification process. |
Assets already in Physical Verification Process | Specify the number of days in the Assets already in Physical Verification Process field. The Assets that are reconciled within the specified days, are excluded from the Physical Verification process. |
FREQUENCY | |
Schedule Type | Select the type to schedule the Physical Verification. You can schedule it One Time or More than One Time (Recurring).
|
Next Verification Date | Specify the subsequent Date when you want the Physical Verification process to be executed. |
Occurs Every | Specify the Monthly or Yearly frequency when the you want the Physical Verification process to be executed. |
ACTIONS
This section explains all the icons displayed on the ACTIONS panel of the ASSET PHYSICAL VERIFICATION page.
SHOW LIST
Click SHOW LIST to display the LIST table showing all the configured Physical Verification Schedules of the Assets. The ASSET PHYSICAL VERIFICATION page is displayed.
Figure: ASSET PHYSICAL VERIFICATION list page
To update a Physical Verification schedule, click the required Request Type. Make appropriate changes and click SUBMIT.
Note:
When the Physical Verification schedule list are displayed under the LIST table, the following actions are displayed on the ACTIONS panel:
- Filters: Click Filters to specify a filter criteria to view a particular set of Physical Verification schedules.
Figure: FILTERS pop-up page
- ADD NEW: Click ADD NEW to create a new Physical Verification schedule.
Confluence Cloud Migration Alert: Please refer to known issues you may encounter in Confluence Cloud: https://eitdocs.atlassian.net/wiki/x/wDGwAQ