The Project Management module enables the Project Managers to define customers, create projects, task lists, and task activities for an organization. It is a flexible tool that supports handling of complete project management tasks. You can also configure project estimation details, time sheet configuration details, and mail configuration details.
The following topics are covered under Project.
Creating a New Project
The New Project feature enables project managers to create a new project and specify the details of the project such as project name, customer name, start and end date, billable type, and so on. You can also define estimation, time sheet, and mail notification configuration details for a project.
To create a new project, perform the following steps.
Navigate to Project > User > Projects > New Project.
Figure: Project page
2. The Project Template needs to be selected before proceeding.
Figure: Project Template.
For further information on the Project Template, refer the field description table below.
Field | Description |
|---|---|
General | Choose the template to create a new Project without a Template. |
Import Microsoft Project | Specify the option when the Project must be imported from Microsoft Project. |
Import Excel Project | Specify the option when the Project must be Imported from Excel. |
Copy from Existing Project | Choose the option if an existing Template has to be chosen for creating the Project. |
3. When the General Template is chosen, the Project Details page is displayed.
Figure: Project Details
4. On the Project Details page, enter the required details.
For more information about the fields and icons on the Project Details page, refer the table below.
Field | Description |
|---|---|
Project Name | Enter a unique name of the project. |
Project Code | Enter a unique Code for the project. |
Customer | Specify a Customer name from the lists the configured customer names that are added using Common Masters feature. Select a customer name under which you want to create a project. |
Department | Choose the Department for which the Project is being created. |
Status | Lists the Project Stage options as:
· Not Started: Indicates that the project is not yet started. · In Progress: Indicates that the project activities have been started and in progress. · Deferred: Indicates that the project is on hold. · Cancelled: Indicates that the project is cancelled permanently. · Released: Indicates that the project is in release cycle. · Closed: Indicates that the project is completed.
Select any one of the options from the list box based on the stage of the project. |
Planned | Specify the planned date for the project. You can also click the Calendar icon to select an appropriate date. |
Actual – Need to check | Specify the Actual date for the project. You can also click the Calendar icon to select an appropriate date. |
Classification | Choose from the drop down menu if the Project is Billable or Non Billable. |
Project Manager | Enter the name of the Project Manager concerned for the Project. |
Location | Choose the Location from the drop down menu. |
Cost | Specify the cost of the Project and the currency. |
Man Hours | Enter the required Man Hours estimated for the Project. |
Process Model | Choose the Process Model from the drop down Example: Agile or Waterfall |
Description | Give a brief description of the Project. |
Active | Enable the Active checkbox. |
Modifying Project Details
The Project List feature allows the Project Manager to Modify the Project details. To Modify Project Details, perform the following steps.
Navigate to Project > User > Projects > Project List.
Figure: Project List pageThe existing list of configured projects are displayed.
Click the Project Name link to view the details of the Project.
Figure: Project Details page
Click the icon to Edit/Modify the Project Details.
The project details are updated, and the following message is displayed: Successfully updated the project details.
Copying Project Details from Existing Projects
The Copy from Existing Project feature enables the project managers to copy project details from an existing project. You can use this option when you feel you have to make similar data entries for a project or when you are creating multiple projects for the same customer.
To copy project details from an existing project, perform the following steps.
Navigate to Project > User > Project > New Project.
Choose the General Template from the Template list.
The Project Details list is displayed as given below.
Figure: Copy icon on Project Details page
4. Choose the highlighted icon to copy the details of an existing Project.
Figure: Copy Project
5. Double click the Project Name and the details will be added on to the Project Details page.
Viewing Project List
The Project List feature enables you to view the all the projects that are created for various customers.
To view the Project List, perform the following actions.
Navigate to Project > User > Projects > Projects List.
On the Project List page, enter the search criteria to filter the project list, if required.
Note: By default, the projects with In Progress stage and Active status are displayed on this page.
Figure: Project List Page
For more information about the fields and icons on the Projects List page, refer the field description table below.
Field | Description |
Delete | The check box which can be enabled to delete the project. |
Project Code | The unique code for each Project. |
Project Name | The name of the Project specified while creating the Project |
Customer | The Customer for whom the Project has been created. |
Start Date | The Start Date of the Project specified while creating the Project |
End Date | The End Date of the Project specified. |
Project Classification | The classification based on whether the Project is Billable or Non Billable. |
Project Manager | The Project Manager assigned to the specific Project |
Status | The stage at which the Project is currently. |
|
|
Filter Icon | The Filter Icon can be used to filter the Project list on the basis of the specified criterion. Example: Customer, Department, Status.
|
Configure Columns | Choose the option to remove columns from the List view. |
Add New | Specify the option to create a new Project. |
Delete | Choose the option to delete the selected Project. |
Export to Excel | Choose the option to Export the Project details to Excel. |
Export All | Specify the option to Export all the listed Projects to excel. |
Field | Description |
Delete | The check box which can be enabled to delete the project. |
Project Code | The unique code for each Project. |
Project Name | The name of the Project specified while creating the Project |
Customer | The Customer for whom the Project has been created. |
Start Date | The Start Date of the Project specified while creating the Project |
End Date | The End Date of the Project specified. |
Project Classification | The classification based on whether the Project is Billable or Non Billable. |
Project Manager | The Project Manager assigned to the specific Project |
Status | The stage at which the Project is currently. |
Filter Icon | The Filter Icon can be used to filter the Project list on the basis of the specified criterion. Example: Customer, Department, Status.
|
Configure Columns | Choose the option to remove columns from the List view. |
Add New | Specify the option to create a new Project. |
Delete | Choose the option to delete the selected Project. |
Export to Excel | Choose the option to Export the Project details to Excel. |
Export All | Specify the option to Export all the listed Projects to excel. |
Managing Tasks
The New Task feature enables project managers to create tasks for the projects. Using this feature you can add, modify, and delete tasks for a project.
You can perform the following tasks using New Task feature:
Creating a New Task
Creating Child Task
Rename
Deactivate
Edit Task
Edit Activities
Add Activity
Figure: Project Task Creation
Creating a New Task
To create a new task, perform the following steps.
Navigate to Project > User > Projects > Project List.
Select the Project
On the left pane under Task List, Enter the task name.
Right click on the Task to get more options.
Figure: Task pane
The following actions can be performed using the Task List.
Field | Description |
|---|---|
Create Task | The user can create a Task using the control |
Create Child Task | The user can create a Child Task under specific Tasks. |
Rename | The Task can be Renamed using this feature. |
Deactivate | The Task can be deactivated using this control. |
Edit Task | This feature helps to Edit Task. |
Edit Activities | Activities can be Edited using this control. |
Add Activity | A new Activity can be added to a Task/Sub Task. |
Creating a Child Task
A child task is created as a Sub Task to the existing Task. To configure the child task, perform the following steps.
Navigate to Project > User > Projects > Project List.
Select the Project.
Under the Task list, right click on a Task.
Click Create Child Task
A Child Task gets created under the main Task.
Creating an Activity
A child task is created as a Sub Task to the existing Task. To configure the child task, perform the following steps.
Navigate to Project > User > Projects > Project List.
Select the Project.
Under the Task list, right click on a Task.
Click Add Activity
A new Activity gets created under the main Task and the following window is displayed.
Fill in all the required fields and SUBMIT.
The Activity gets created under the Task.
Figure: Add Activity
For more information on the Add Activity fields, refer the table below.
Field | Description |
|---|---|
Description | Enter a brief description of the Activity planned. |